Critics: Duke trying to shift more Indiana plant cost….

  INDIANAPOLIS (AP) _ A consumer group says Duke Energy is trying skirt an agreement capping how much of the cost overruns electric customers must pay on its new coal-gasification plant in southwestern Indiana.
 
  That follows Duke confirming the plant in Edwardsport was shut down for repairs starting six days after the company declared it operational in early June. Duke spokeswoman Angeline Protogere tells The Indianapolis Star that the plant has been generating power intermittently since July 9.
 
  Citizens Action Coalition director Kerwin Olson says Duke is trying to force ratepayers into paying for the cost of repairs that should be considered part of the plant's construction.
 
  State regulators have limited Duke to collecting about $2.6 billion of the plant's $3.5 billion construction cost from customers.
 
  Duke denies any misconduct.
 

Related posts

Order Implementing Online Filing in All Indiana Appellate Courts

Kylie Havens

Calls To Enforce Iran Steel Sanctions Plentiful Among U.S. Senators

Michael McIntyre

Pence Says Gambling Regulators Need to Use ‘Common Sense’

Tom Franklin